When scheduling out your crews you may have a job that requires multiple days per stage. In these cases, follow the article below for steps on how to go about scheduling your team.
- Navigate to the Jobs module using the menu at the top of the screen.

- Select the job that you are trying to schedule.

- In the job's Main Information page, select the Stage on the left that you are scheduling multiple days for.

- On the stage header, select the [ + ] icon and then select the task you need an additional day for.

- On the new task line, select Schedule to assign the crew needed on the new day.

- Use the scheduler to select the date and crew needed, as well as the work hours, before selecting Send.

- Once scheduled, navigate to the Workload module.

- Any multi-day jobs should appear with a jagged edge indicating the work continues past that date, or work already happened prior to that date.